Commercial Construction : ABN Leederville Update June 2020
Commercial Construction : ABN Leederville Update June 2020The Leederville Office Building is taking shape. there are now windows to the South Laneway as the FMA Facades team have commenced the first glazing installation, which are visible from Oxford Street. By mid-July, the curtain walling is expected to be complete. The Ground Floor face brickwork has been completed by PWD Bricklayers and Level 1 is well underway.
Inside the building, the mechanical (MPM Mechanical), electrical (TES Electrical) and hydraulic (Nemjon Plumbing) fit-out is progressing with the Western Power substation internal work ready for inspection.
There is a total of 90 workers on site at present, 69392 man hours worked so far, total volume of concrete poured is 7500m3 and 890 tonnes of reo installed.
Text information by PACT Construction.